O’Shaughnessy Dam Bridge Replacement
Dublin, Ohio
- Owner: City of Columbus Department of Public Works
- Constructed: 1989 – 1993
- Original Contract Amount: $4,325,000
This challenging project included complete removal and replacement of a concrete bridge carrying traffic across the existing O’Shaughnessy Dam. The work included demolition of the existing structure, construction of new piers on top of the existing dam spillway, and construction of a box beam superstructure with a composite concrete deck and architectural precast concrete railings to replicate the original structure.