Projects
Southerly Waste Water Treatment Plant Headworks
Columbus, Ohio
- Owner: City of Columbus
- Constructed: 2003 – present
- Original Contract Amount: $50,868,825
Project consists of construction of a new Raw Sewage Pump Building with four mechanically cleaned bar racks, four 48" raw sewage pumps with variable frequency drive units and motors, sluice gates, four 48" diameter magnetic flow meters, belt conveyor, elevator, plumbing, HVAC, mechanical, electrical, instrumentation and control systems. Construction included installation of a 1,500 foot long sheet pile cut-off wall for flood protection, mass excavation, and dewatering of the site. Projected completion in 2007.